State Farm Arena (formerly Philips Arena)

Contractor
ATL JV, Turner Construction Company, AECOM Hunt, SG Contracting & Bryson Constructors
Project Dates
3 Phases: June-October 2017-October 2018
Project Location
Atlanta, GA

Over twenty years, after completing the original construction cleaning for Philips Arena, CCS was proud to be a part of the team again when the arena underwent renovations. The project was completed in 3 phases prior to 2018-2019 NBA season. A $200 million renovation and makeover of the interior of the arena. The extensive renovation included expanding and opening up the concourses to the bowl, new construction of lounges and bars with an emphasis on fan experience such as The Atlanta Social Club, The Zac Brown’s Social Club, Killer Mike’s SWAG Shop, and the NBA’s first courtside bar. The renovation also upgraded the existing suites, concessions, and restrooms.